SBM completes the contract to supply, install, and upgrade the backup generator system for CMC Corporation’s Data Center at the Ho Chi Minh City High-Tech Park.
On June 20, 2024, SBM completed the contract ahead of schedule by producing-assembling, supplying and installing an additional SBMPOWER-FPT 550 KVA along with a synchronization system connected to the existing system, increasing the total capacity to nearly 3000 KVA. In 2018, SBM had provided and installed two SBMPOWER-PERKINS 550 KVA at this location.
Given the crucial nature of the power source serving the Data Center, the CEO of SBM personally inspected, urged and supervised the process at the site. Selecting SBMPOWER generators for CMC’s important Central Data demonstrates that SBM’s products and services deliver reliable, high-quality power for essential projects.